EETC to implement EGP 440m substation in west Damietta

Mashaly added that the plant is to be built within 12 months from the contract date.


The Egyptian Electricity Transmission Company (EETC) has signed a contract with the Al Kharafi-Taikai-NHVS consortium to construct a transformer substation in west Damietta valued at EGP 440m.

Chairperson of the EETC, Sabah Mashaly, said that the contract involves the establishment of 22/220/500kv to meet the increasing electricity needs in the Delta region.

Mashaly added that the plant is to be built within 12 months from the contract date.

In a related context, El Sewedy Electric announced it will complete the implementation of a 500kv overhead power line with a length of 185 km within weeks.

A source at the Ministry of Electricity told Daily News Egypt that the new Benban-Nagaa Hammadi line will transfer electricity produced from the projects of the solar energy feed-in tariff in Aswan.

The source added that the Upper Egypt Electricity Distribution Company has completed the implementation of a power transformer with a capacity of 500kV and was operational until the completion of the expansion of the Benban transformer plants implemented by XD-EGEMAC to transfer the electricity produced from the solar power stations to the energy grid.